‘Lightning fast’ timeline will bring big changes to 82nd Avenue

A slew of safer crossings on 82nd Avenue are expected to be constructed next year.
(Photo: Jonathan Maus/BikePortland)

After years of advocacy, the City of Portland finally wrested control of 82nd Avenue from the State of Oregon and has secured $185 million to spend on it.

“Moving through the entire process and being completely finished in five years is lightning fast.”
— Kristin Hull, PBOT

Now comes the hard part: They have just five years to plan and build many of the long-awaited projects.

The first phase of the project will spend $80 million allocated by the City of Portland through the federal American Rescue Plan Act, which comes with strict time constraints. According to comments from Portland Bureau of Transportation staff at a meeting of their bicycle and pedestrian advisory committee meetings last month, instead of the 7-10 year horizon that’s common for major capital transportation projects, all of the ARPA funds for this overhaul of 82nd Avenue must be obligated by 2024 and completely spent by the end of 2026.

“I’m really nervous about the timeline,” said PBOT Planning Division Manager Kristin Hull at that advisory committee meeting on December 14th. “Moving through the entire process and being completely finished in five years is lightning fast. And so we are going to meet that timeline… I’ll keep saying that over and over again. Because it is so present in my mind at all times.”

As of today (1/19), PBOT will have a lot more help to do it. They just agreed to award an $8 to $12 million consulting contract to KPFF Inc. for architectural and engineering services on what they’re calling the 82nd Avenue Investment Program.

To refresh, this project will encompass a large slate of updates to the former state highway (which was neglected by ODOT after the construction of I-205 about 10 blocks east). The Oregon Legislature has agreed to fund the project to the tune of $80 million, which will allow PBOT to bring it up to a “state of good repair” and complete the transfer.

Advertisement


(Slides shown at December 14th joint meeting of PBOT bicycle and pedestrian advisory committees.)

“82nd Avenue is a defining roadway in Portland and is located in one of the most diverse areas of the state,” reads a description of the project in the PBOT request for proposals (RFP) won by KPFF. “It is a regionally significant transportation corridor, hosting one of TriMet’s busiest bus lines, serving 20,000 to 30,000 vehicle trips a day, and providing a critical north-south connection.”

Also at last month’s meeting, Hull and PBOT Senior Planner Julia Reed outlined the phased approach PBOT plans to take.

Phase 1 planning and outreach has already begun. It will consist of $80 million in “critical safety and maintenance” projects along a seven-mile stretch of 82nd. Between SE Clatsop and NE Killingsworth, PBOT estimates they’ll build six to 10 new “enhanced crossings” ($10-$12 million), about nine “intersection safety enhancements” ($8-$10 million)and make significant upgrades to lighting ($10-$12 million) and sidewalks/ADA curb ramps ($43-$50 million) along large sections of the corridor.

PBOT Planner Julia Reed said the impact of these initial investments will be “amazing”, but also said the Metro 2020 funding measure process identified a total investment need of $500 million to do everything the community wants.

Timeline

Larger-scale changes, like a rapid bus system, new lane configuration, changing the width of the street, and so on, will have to wait until Phase 2, which PBOT calls, “Building a Better 82nd”. Both phases will happen simultaneously with initial outreach on Phase 2 slated to begin this coming spring and construction to begin in 2027.

Questions from committee members hinted at robust discussions to come during Phase 2 planning.

Bicycle Advisory Committee member Iain MacKenzie brought up the idea of bike lanes and wider sidewalks on 82nd. “How are you planning to make sure that whatever’s built with the short-term safety projects don’t preclude more aspirational things in the longer term?”, he asked. (Hull responded that PBOT is aware of that issue.)

BAC Chair David Stein asked Hull how they’ll decide what type of facilities can and cannot be included in the future of 82nd. “We’ll need to have that conversation very carefully,” Hull responded. “And look at the needs for transit and the needs for motor vehicles and the needs for pedestrians and cyclists and really work through those in a structured way… It’ll be a careful discussion.”

Jonathan Maus (Publisher/Editor)

Jonathan Maus (Publisher/Editor)

Jonathan Maus is BikePortland’s editor, publisher and founder. Contact him at @jonathan_maus on Twitter, via email at This email address is being protected from spambots. You need JavaScript enabled to view it., or phone/text at 503-706-8804. Also, if you read and appreciate this site, please become a supporter.

(Originally posted by Jonathan Maus (Publisher/Editor))